Tentative Schedule

updated as of October 26th, 2018
Event:
Anticipated Date:
Public Stakeholders Meeting
March 26, 2014
Public Information Meeting
November 6, 2014
NEPA & Plans Public Hearing
February 25, 2016
Anticipated Project Funding Complete
February 2017
RFP Advertised
July 2017
Design-Build Contractor Hired
February 2018
Public Information Meeting
April 2018
Start of Site Preparation
June 2018
Plans, Permits Complete by Contractor
June 2018
VDOT Approval of Plans
June 2018
Trail Detours Begin
July 16, 2018
Street Detours Begin
July 16, 2018
Start of Demolition
July 2018
Start of Construction
September 2018
Street Re-Opened to Vehicles
March 2019
Substantial Completion
April 2019
Trail Re-Opened
May 2019
Completion of Construction
June 2019
Dedication of New Bridge
July 2019
Project Closeout
July - Sept. 2019